Tees Valley courts contractors on £1bn five-year transport pipeline

The combined authority has opened market engagement on a 2027–2032 programme of road, rail and bus schemes, weighing multiple contracts and a possible programme-wide alliance.

Marianne DelacroixNovember 12, 20265 min read14 views
Concept illustration of a regional transport corridor combining a new road, a rebuilt rail platform and a bus interchange, representing a multi-scheme building programme.

The Tees Valley combined authority has submitted its five-year transport wish-list to the Department for Transport and is now asking construction firms how the potential work should best be packaged for procurement.

The programme, billed at £1bn, is scheduled to run from April 2027 to March 2032 and spans major road schemes, railway upgrades, bus infrastructure, active travel and transport technology. The government has already confirmed £978m of core transport funding for the region, but the wider list includes projects that still require further business case approvals and additional financial backing.

Because the pipeline mixes schemes at different stages of readiness, the volume of construction work eventually let will depend on how many projects clear those approval and funding hurdles.

Schemes on the list

  • Darlington Northern Link Road
  • upgrades to the A66 and A689 corridors
  • a new platform at Middlesbrough Station
  • redevelopment of Thornaby Station
  • a new station at Teesside International Airport
  • improvements to Middlesbrough bus station
  • transport links serving the Teesworks development

The authority has acknowledged that delivering the full programme will depend on government support and potentially further outside funding. Steve Harker, the combined authority's cabinet member for transport and infrastructure, said it is crucial that people understand that, while the body is devolved, major transport schemes often require significant additional funding. Government backing for the plans is vital, he added, because it would allow external bodies to help fund the programme and give the region the best chance of delivering as many projects as possible in good time.

Procurement shape under discussion

Despite the funding uncertainties, the authority is pressing ahead with early supplier engagement to prepare its procurement strategy. It expects to let multiple contracts covering highways, rail, civil engineering and specialist infrastructure rather than award one giant deal, a structure that would spread the work across several disciplines and firms.

The authority is also considering a programme-wide alliance built on the FAC-1 Framework Alliance Contract model, which would bring delivery partners together and is intended to encourage regional contractors and SMEs to participate in the pipeline.

An initial supplier launch event was held on 9 November, and firms are now invited to provide feedback through a market engagement questionnaire. Contractors have until 1 March 2027 to respond.