Home & Garden

Greenhouse Growers Advised to Prepare Curtailment Plans for Grid Emergencies

Utility outage groups show where a site stands in a load-shedding queue; a written plan lets growers choose which equipment stops, is reduced or stays on.

Leocadia MwangiNovember 10, 20265 min read13 views
A commercial greenhouse interior at dusk with rows of crops, ventilation fans, irrigation pumps, heating pipes and a control cabinet; outside, power lines and a substation stand under a stormy sky.

Commercial greenhouses have a place in their utility’s emergency load-shedding plan whether or not the utility prints it on the bill. In California, bills can show a rotating outage group or block, indicating where a site falls in line when the grid runs short. Federal reliability standards (NERC’s EOP-011) require grid operators nationwide to maintain plans for cutting load, but California is unusual in putting the group information directly on customer bills.

When such plans are used, power is shut off systematically, often with minutes of warning. Hospitals and other critical facilities are protected where possible; most other customers, including greenhouses, are not. Rolling outages have affected several regions in recent years during heat waves and winter storms. For a greenhouse, that can mean fans, pumps, irrigation, heating and controls go dark at the worst time.

Outage versus curtailment

The difference is control. In an outage, everything stops at once. In a planned curtailment, the grower decides in advance which loads drop, by how much, and which stay on to protect the crop. A curtailment plan is a written plan for the hours when the grid is under stress.

Four planning steps

  • List equipment and load. Record major equipment and roughly how much power each draws: supplemental lighting, fans, evaporative cooling, heating, pumps, dehumidification, controls and cold storage.
  • Sort loads. Some can be dropped entirely for a few hours without harm; some can be reduced by dimming lights, staggering fans or adjusting a setpoint a few degrees; controls, alarms and whatever keeps the most sensitive crop alive must stay on. The sorting depends on crop and stage and can change through the season.
  • Use forecasts as triggers. Outage orders may arrive with minutes of notice, but heat waves and cold snaps are forecast days ahead and grid operators usually issue public alerts before an emergency. In summer, growers can pre-cool in the morning, irrigate early and close shade curtains before the afternoon peak. In winter, they can heat ahead of the cold peak, close thermal curtains early and make sure backup heat is fueled and tested.
  • Assign roles and automate. Decide who receives the alert, who makes the decision and who carries it out. If an environmental controller can run the sequence automatically, program it and test it. A plan that depends on a single person answering a call on a weekend afternoon is not a plan.

After those steps, a grower should know how many kilowatts can be given up, for how long and at what cost to the crop. That figure is what the grid is willing to pay for. Before ordering outages, utilities and grid operators will pay customers who agree in advance to cut load, because a megawatt that disappears on request is cheaper than one bought at emergency prices. That market is demand response, and it exists in most of the country, largely so the outage plan never has to be used.

Growers should ask their utility where their site falls in its plan and then start making their own.